Metro · Phase 2A

Bangalore Metro Phase 2A: Central Silk Board to KR Puram on the ORR

Published:
30 September 2026
Last updated:
4 October 2026
Last verified:
3 October 2026
Author:
PropertyVest Research Desk
Read:
8 min

Quick answer

Phase 2A is a 19.75 km elevated Blue Line corridor with 13 stations along the eastern Outer Ring Road from Central Silk Board to KR Puram. It puts Bellandur, Kadubeesanahalli, Marathahalli and Doddanekkundi on the metro map and interchanges with the Yellow Line at Silk Board and the Purple Line at KR Puram.

Introduction

The stretch of Outer Ring Road between Silk Board and KR Puram carries some of the densest office space in India and some of the slowest peak-hour traffic in the country. Phase 2A of Namma Metro is the direct answer: an elevated line over the same road, with stations next to the tech parks that generate the jams. For homebuyers, this corridor decides whether Bellandur, Kadubeesanahalli and Marathahalli stay commute-constrained or become genuinely convenient addresses.

Below we cover the alignment, the stations, the interchanges that make it useful, construction status, and a realistic view of what it does to prices and rents.

Key takeaways

Length
About 19.75 km, elevated
Stations
13
Route
Silk Board to KR Puram along eastern ORR
Interchanges
Yellow Line and Purple Line
Authority
BMRCL
Key beneficiaries
Bellandur, Marathahalli, HSR Layout

Project status

Under construction

Status reflects the latest publicly available information from the implementing authority. Proposed and approved stages are not the same as construction or operation — PropertyVest does not present a proposal as confirmed.

Quick facts

Key facts about Bangalore Metro Phase 2A
ProjectBangalore Metro Phase 2A
TypeMetro rail
LocationOuter Ring Road, Bengaluru
Approx. lengthAbout 19.75 km
CorridorsBlue Line (Phase 2A)
Stations13
Current statusUnder construction
AuthorityBMRCL
Expected timelineNot publicly confirmed
Last updated4 October 2026

What is Bangalore Metro Phase 2A?

Phase 2A is part of the Blue Line, built by BMRCL. It is fully elevated, about 19.75 km long with 13 stations, following the eastern arc of the Outer Ring Road.

Why it matters more than its length suggests

Almost every large office campus on the eastern ORR sits within a kilometre of the alignment. Today an employee in HSR Layout or Marathahalli can spend longer travelling 8 km than someone commuting 25 km on a highway. Two interchanges make it a network line rather than a shuttle:

  • Central Silk Board — Yellow Line towards Electronic City and the city core.
  • KR Puram — Purple Line towards Whitefield and MG Road; Phase 2B continues north to the airport.

Station catchments

HSR Layout, Agara, Iblur, Bellandur, Kadubeesanahalli, Marathahalli, Doddanekkundi and Mahadevapura. Housing here is mature, so the metro mainly strengthens existing rental demand.

Construction on the ground

The viaduct is being built over a saturated road, bringing lane closures and diversions. Visit any ORR project at peak hour, twice, before deciding.

Route & coverage

Central Silk Board → HSR Layout → Agara → Ibbaluru → Bellandur → Kadubeesanahalli → Kodibisanahalli → Marathahalli → ISRO → Doddanekkundi → DRDO Sports Complex → Mahadevapura → KR Puram.

Stations, junctions & corridors

Station / junctionLocalityCorridorNotes
Central Silk BoardSilk BoardBlue LineYellow Line interchange
HSR LayoutHSR LayoutBlue LineDense rental catchment
AgaraAgaraBlue LineSarjapur Road access
BellandurBellandurBlue LineLargest office catchment
KadubeesanahalliKadubeesanahalliBlue LineTech park belt
MarathahalliMarathahalliBlue LineRetail and mid-market hub
MahadevapuraMahadevapuraBlue LineWhitefield approach
KR PuramKR PuramBlue LinePurple Line interchange

Timeline

  1. 2017–2019

    Corridor approved and tendered

    Completed
  2. 2021 onwards

    Pier and viaduct work along ORR

    Completed in stretches
  3. Ongoing

    Station finishing, track and signalling

    In progress
  4. Not confirmed

    Commercial opening

    Not confirmed

Timelines for large infrastructure projects change. Entries labelled expected or reported are not guaranteed completion dates.

Real estate impact

Property prices

Resale homes within a kilometre of Bellandur, Kadubeesanahalli and Marathahalli stations already quote a premium — the corridor was announced long ago. Remaining upside is more likely in older or set-back stock not yet re-rated.

Rental market

This is primarily a rental corridor. ORR tenants pay for minutes, so station-adjacent 2 and 3 BHK homes should see shorter vacancy once services begin.

Infrastructure may support prices, rentals and liquidity, but outcomes depend on delivery timelines, supply and broader market conditions. PropertyVest does not guarantee appreciation or returns.

Property price & rental context

Price and rent context for this corridor is published with the date of the data it is based on.

Localities connected to Bangalore Metro Phase 2A

Projects in areas connected to this infrastructure

Habulus Oasis Grove — Electronic City

Habulus Oasis Grove

Habulus Groups · Electronic City

  • Configurations: Details being verified
  • Price: ₹1.13 Cr
  • RERA: Details being verified
  • Status: New Launch
View project

Orchid South Park

Goyal & Co · Electronic City

  • Configurations: Details being verified
  • Price: ₹1.44 Cr
  • RERA: PRM/KA/RERA/1251/308/PR/060526/008625
  • Status: New Launch
View project

Elv The Ivory Terraces

ELV Projects · Whitefield

  • Configurations: Details being verified
  • Price: ₹1.10 Cr
  • RERA: PRM/KA/RERA/1251/446/PR/181122/005469
  • Status: New Launch
View project

Habulus Tranquil

Habulus Group · Electronic City

  • Configurations: 2 BHK, 2.5 BHK, 3 BHK
  • Price: ₹0.98 Cr
  • RERA: PRM/KA/RERA/1251/310/PR/020126/008378
  • Status: Under Construction
View project

Investment outlook

For end-use it is an easy yes if the commute matches. For investment, prefer set-back stock at a discount, verify actual walking access to the station entrance, and underwrite on today's rent.

Potential benefits

  • Serves the ORR office belt where road commuting is worst
  • Two interchanges enable city-wide trips
  • Mature housing means immediate tenant demand
  • Improves resale liquidity of older ORR stock
  • Cuts dependence on cabs and office shuttles

Risks & considerations

  • No committed opening date
  • ORR disruption continues until systems work ends
  • Frontline prices already reflect much of the benefit
  • Walking access to stations is poor in several pockets
  • Lake-area civic issues in Bellandur remain

PropertyVest publishes risks alongside opportunity. Infrastructure timelines and property outcomes are not guaranteed.

Conclusion

With Phase 2A and 2B running as one Blue Line, an ORR employee reaches the airport by rail — turning the eastern ORR from a traffic liability into a connected spine.

Frequently asked questions

How many stations does Phase 2A have?

Thirteen, across about 19.75 km between Central Silk Board and KR Puram.

Which localities does it serve?

HSR Layout, Agara, Iblur, Bellandur, Kadubeesanahalli, Marathahalli, Doddanekkundi, Mahadevapura and KR Puram.

Does it connect to other lines?

Yes — the Yellow Line at Silk Board and the Purple Line at KR Puram.

When will Phase 2A open?

Targets have been revised several times; treat no date as fixed until BMRCL announces commercial operations.

Will it reduce ORR traffic?

It will shift a share of office commuters off the road but will not remove congestion entirely.

Should I buy on ORR before it opens?

Only if the property works today on price, title and developer record.

Sources & verification

About PropertyVest & this article

PropertyVest is a Bangalore-focused property advisory. We track infrastructure delivery, locality pricing and project approvals across the city so buyers can compare options on facts rather than on brochure claims.

Written by
PropertyVest Research Desk
Reviewed by
PropertyVest Editorial
Published
30 September 2026
Last updated
4 October 2026
Facts last verified
3 October 2026

This article is research and general information, not investment advice. Verify approvals, RERA registration and current pricing before you transact.

Not sure how this corridor affects the property you're considering?

Talk to a PropertyVest advisor for a locality-specific read on connectivity, pricing and rental demand.